nerdexam
PMIPMI

PMP · Question #1138

PMP Question #1138: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1138. The question stem and answer options stay visible for context.

Submitted by amina.ke· Apr 18, 2026Process

Question

During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected. What should the project manager do?

Options

  • APerform a root cause analysis of the project performance.
  • BAdjust the original budget estimates with the current cost variance.
  • CReview the activity duration to reforecast the project completion date.
  • DNegotiate the project changes and adjust stakeholder expectations.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Cost Management#Variance Analysis#Root Cause Analysis#Performance Monitoring
Full PMP PracticeBrowse All PMP Questions