nerdexam
PMIPMI

PMP · Question #1137

PMP Question #1137: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1137. The question stem and answer options stay visible for context.

Submitted by akirajp· Apr 18, 2026People

Question

A project team was asked to resume development activities on a project that was suspended for a few months due to the fast-changing environment and conditions. What should the project lead do?

Options

  • AReview the items remaining in the backlog with the project team
  • BAsk the project team to approve all of the remaining backlog items
  • CAsk the program manager to approve the backlog with the client
  • DReview the items remaining in the backlog with the project sponsor

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Project Resumption#Backlog Management#Agile Planning#Team Collaboration
Full PMP PracticeBrowse All PMP Questions