A project is in the final stages, and a key stakeholder demands a change to a product feature that will add 2 weeks to the critical path. What should the project manager do?

Options

  • AInitiate a risk response strategy from the risk register.
  • BPerform a detailed assessment to analyze the impact.
  • CReject the changes as the project is in the final stages.
  • DUse schedule compression methods to alter the critical path.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Change Control#Impact Analysis#Stakeholder Management