PMIPMI
PMP · Question #1132
PMP Question #1132: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1132. The question stem and answer options stay visible for context.
Submitted by katya_ua· Apr 18, 2026Process
Question
A project is in the final stages, and a key stakeholder demands a change to a product feature that will add 2 weeks to the critical path. What should the project manager do?
Options
- AInitiate a risk response strategy from the risk register.
- BPerform a detailed assessment to analyze the impact.
- CReject the changes as the project is in the final stages.
- DUse schedule compression methods to alter the critical path.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Change Control#Impact Analysis#Stakeholder Management