nerdexam
PMI

PMP · Question #1102

A product is undergoing its last iterative increment, and the project team is ready to make the final deployment. The company's financial manager is asking the project team to complete the deployment

Sign in or unlock PMP to reveal the answer and full explanation for question #1102. The question stem and answer options stay visible for context.

Submitted by ahmad_uae· Apr 18, 2026Process

Question

A product is undergoing its last iterative increment, and the project team is ready to make the final deployment. The company's financial manager is asking the project team to complete the deployment and close the project as soon as possible so it can be capitalized. What should the project manager do?

Options

  • AExpedite the final deployment and close the project.
  • BIgnore the stakeholder's request as there is a defined plan.
  • CUpdate the acceptance criteria for the iteration.
  • DCheck on the definition of done (DoD) for the project.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Definition of Done#Project Closure#Stakeholder Engagement#Agile Practices
Full PMP Practice