PMP · Question #1097
PMP Question #1097: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1097. The question stem and answer options stay visible for context.
Question
A project manager is in charge of a software development project. A key stakeholder complains that they never received the functionality test status reports. The project manager provides the reports, and the stakeholder notices that an important functionality for their area was not tested. Which tool should the project manager have used to prevent this situation?
Options
- AIssue log
- BProject scope statement
- CStakeholder register
- DProject charter
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.