Question

A team is not delivering the committed work. Cards are not moving on the kanban board, and the burndown chart shows that the sprint progress is slow. What should the agile project manager do?

Options

  • AConsider the use of alternative performance metrics.
  • BChange the work in progress (WIP) limit to reflect the team's capacity.
  • CDiscuss the performance with senior leadership.
  • DMeet with the project team members who are slow in delivering tasks.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Agile Performance Management#Team Coaching#Impediment Identification
Full PMP PracticeBrowse All PMP Questions