Question

A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee: Actual progress = 2 units Planned progress = 3 units Actual cost (AC) = 2 units Budgeted cost = 3 units What statement should the project manager make to the project steering committee?

Options

  • AThe project is currently behind schedule but at a lower cost, and an application for a time and
  • BThe project is currently behind schedule with a corresponding cost savings, and no further actions
  • CThe project is currently behind schedule with a corresponding lower cost, and every effort is being
  • DThe project is currently behind schedule but is under the planned expenditure, and the project

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Performance Reporting#Schedule Performance#Cost Performance#Stakeholder Communication
Full PMP PracticeBrowse All PMP Questions