PMIPMI
PMP · Question #1072
PMP Question #1072: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1072. The question stem and answer options stay visible for context.
Submitted by yaw92· Apr 18, 2026Process
Question
A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee: Actual progress = 2 units Planned progress = 3 units Actual cost (AC) = 2 units Budgeted cost = 3 units What statement should the project manager make to the project steering committee?
Options
- AThe project is currently behind schedule but at a lower cost, and an application for a time and
- BThe project is currently behind schedule with a corresponding cost savings, and no further actions
- CThe project is currently behind schedule with a corresponding lower cost, and every effort is being
- DThe project is currently behind schedule but is under the planned expenditure, and the project
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Performance Reporting#Schedule Performance#Cost Performance#Stakeholder Communication