PMIPMI
PMP · Question #1051
PMP Question #1051: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1051. The question stem and answer options stay visible for context.
Submitted by tunde_lagos· Apr 18, 2026Process
Question
A project scope was developed with numerous assumptions. During the execution phase, the assumptions changed, which has jeopardized the planned business value of the project. What should the project manager do next?
Options
- ADeliver what was planned in the project management document according to the specifications
- BUpdate the assumptions log and change log, and implement the change control process
- CInform the client that the project cannot meet the project timeline and additional costs will be
- DReport on the changed assumptions to the project sponsor and seek support to prioritize the
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Change Management#Integrated Change Control#Assumptions