PMIPMI
PMP · Question #1046
PMP Question #1046: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1046. The question stem and answer options stay visible for context.
Submitted by jian89· Apr 18, 2026Process
Question
An organization is using a hybrid delivery approach for a complex project. In the iteration review, a senior manager is asking for a complete redesign of the functionality presented. This may require a significant change in the technical architecture and an additional release. What should the project lead do first?
Options
- ADiscuss with the solution architect
- BDiscuss with the product owner
- CDiscuss with the technical lead
- DDiscuss with the development team
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Hybrid Projects#Product Owner#Scope Management#Change Control