PMP · Question #1045
PMP Question #1045: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1045. The question stem and answer options stay visible for context.
Question
A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months. What should the new project manager do?
Options
- AUse a hybrid approach in which agile practices are used but the value is provided to the client at
- BContinue working with the predictive approach to deliver the value at the end of the project.
- CSubmit a change request to the project board to adjust the delivery date to 2 months earlier than
- DMeet with the team to review the backlog and create small iterations that can deliver incremental
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.