nerdexam
PMIPMI

PMP · Question #1023

PMP Question #1023: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1023. The question stem and answer options stay visible for context.

Submitted by valeria.br· Apr 18, 2026Process

Question

A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase. What should the project manager do next?

Options

  • AReview the new requirements with the compliance department to determine if a change request is
  • BProceed with the defined project requirements and delay implementing the new requirements
  • CAdd the new requirements to the project scope immediately since they are mandatory changes
  • DIgnore the new requirements as the current budget and schedule do not allow for any changes

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Change Management#Regulatory Compliance#External Environmental Factors#Stakeholder Engagement
Full PMP PracticeBrowse All PMP Questions