PMP · Question #1022

A project manager has been running an agile project for 6 months and has been reporting that the project is on track every week. However, on the last week before releasing the final product, the…

The correct answer is D. Developed a risk response plan that would have provided options and strategies regarding project. To prevent unforeseen technical impediments from jeopardizing project delivery, the project manager should proactively develop a risk response plan.

Submitted by akirajp· Apr 18, 2026Process

Question

A project manager has been running an agile project for 6 months and has been reporting that the project is on track every week. However, on the last week before releasing the final product, the team found a technical impediment that put the project delivery in jeopardy overnight. What should the project manager have done to prevent this situation?

Options

  • AConsidered historical data from previous projects with similar impediments to help identify the
  • BSought and implemented alternative ways to track progress and impediments to identify potential
  • CProvided technical training to the team in advance to ensure the team had high-level technical
  • DDeveloped a risk response plan that would have provided options and strategies regarding project

How the community answered

(36 responses)
  • A
    6% (2)
  • B
    19% (7)
  • C
    11% (4)
  • D
    64% (23)

Why each option

To prevent unforeseen technical impediments from jeopardizing project delivery, the project manager should proactively develop a risk response plan.

AConsidered historical data from previous projects with similar impediments to help identify the

While historical data is useful for identifying risks, simply considering it doesn't automatically prevent a specific future impediment without a concrete plan of action.

BSought and implemented alternative ways to track progress and impediments to identify potential

Implementing alternative tracking methods might help identify impediments earlier, but it doesn't inherently provide a solution or strategy for addressing them once identified.

CProvided technical training to the team in advance to ensure the team had high-level technical

Providing technical training improves team capability but doesn't guarantee the prevention of all possible technical impediments, especially those that might be external or complex.

DDeveloped a risk response plan that would have provided options and strategies regarding projectCorrect

Developing a comprehensive risk response plan identifies potential risks, such as technical impediments, and outlines proactive strategies and options for how to address them if they occur, preventing last-minute delivery issues. This allows for planned actions to mitigate or resolve the impediment instead of scrambling at the last minute.

Concept tested: Agile risk management and response planning

Topics

#Risk Management#Risk Response Planning#Agile Project Management#Proactive Planning