nerdexam
PMIPMI

PMP · Question #1010

PMP Question #1010: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1010. The question stem and answer options stay visible for context.

Submitted by daniela_cl· Apr 18, 2026Process

Question

A project manager is about to start a large-scale project with unclear requirements, a fixed deadline, and a fixed budget. The client is unable to provide a product owner, as they do not have enough capacity and they want to be involved only a few times during the project. How should the project manager plan and manage the project?

Options

  • AConvince the client that a product owner is needed, as the project manager is not able to run an
  • BDefine the project's requirements, prepare a long-term detailed plan, and manage the project
  • CAgree up front on a minimum viable product (MVP), establish deadlines for review, and run the
  • DRefuse to manage the project as there is too much risk in developing this kind of project without a

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Agile Planning#Requirements Management#Stakeholder Engagement#Adaptive Approaches
Full PMP PracticeBrowse All PMP Questions