Submitted by weili_xi· Apr 18, 2026Continuous Improvement
Question
An agile practitioner notices that team members are disengaged. As a result, the team's velocity has decreased. What should the agile practitioner do to get the team back on track?
Options
- AEscalate the issue to the project sponsor.
- BRemove stories to increase velocity.
- CHold a standup to address the issue.
- DFacilitate a team retrospective.