PMI-ACP · Question #748

The team underestimated the complexity of a story, resulting in new decomposition of the work to be delivered in the current sprint and items to be returned to the backlog. What should the Scrum Maste

Sign in or unlock PMI-ACP to reveal the answer and full explanation for question #748. The question stem and answer options stay visible for context.

Submitted by sofia.br· Apr 18, 2026Continuous Improvement

Question

The team underestimated the complexity of a story, resulting in new decomposition of the work to be delivered in the current sprint and items to be returned to the backlog. What should the Scrum Master do next?

Options

  • AAsk the project manager to work with the product owner to help generate clearer stories in the
  • BDevelop guidelines to prevent future occurrences.
  • CDuring the retrospective, discuss the issue and create an action plan to avoid it in the future.
  • DAllow the team to devise a corrective action without external intervention.

Unlock PMI-ACP to see the answer

You've previewed enough free PMI-ACP questions. Unlock PMI-ACP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Retrospectives#Scrum Master Role#Continuous Improvement#Inspect and Adapt