PMI-ACP · Question #749
Agile team A struggles to deliver committed stories due to technical dependencies with team B, which continuously fails to meet its delivery commitments. What should the agile team lead do?
The correct answer is B. Conduct a vision-sharing session with the teams to communicate the project's overall goals. When teams fail to meet cross-team delivery commitments, the issue is often misaligned priorities or a lack of shared understanding of the overall project goals. A vision-sharing session reconnects both teams to the common purpose and fosters the collaboration needed to resolve…
Question
Agile team A struggles to deliver committed stories due to technical dependencies with team B, which continuously fails to meet its delivery commitments. What should the agile team lead do?
Options
- ACreate a new team to deliver the dependencies, and bring team B under performance
- BConduct a vision-sharing session with the teams to communicate the project's overall goals.
- CSwap team members from both teams so that deliveries are better supported.
- DDiscuss negotiating the delivery timelines with team A.
How the community answered
(15 responses)- A13% (2)
- B47% (7)
- C7% (1)
- D33% (5)
Explanation
When teams fail to meet cross-team delivery commitments, the issue is often misaligned priorities or a lack of shared understanding of the overall project goals. A vision-sharing session reconnects both teams to the common purpose and fosters the collaboration needed to resolve dependency issues. Option A (creating a new team and placing Team B under performance management) is heavy-handed and doesn't address the root cause. Option C (swapping team members) may help transfer knowledge but disrupts both teams without solving the alignment problem. Option D (negotiating timelines with Team A) only accommodates the problem rather than solving it-Team A shouldn't have to adjust because Team B can't deliver.