PMI-ACP · Question #736
After three iterations, it is identified that a project's underlying security structure architecture is unstable. While there is a technical solution, all work to date is flawed. This will impact seve
The correct answer is C. Meet with the team and stakeholders to address rework and rewrite stories as needed.. A foundational architectural defect that invalidates all prior work and threatens future business services is a high-stakes issue that requires collective decision-making. The product owner must bring together the team and stakeholders to transparently assess the scope of rework,
Question
After three iterations, it is identified that a project's underlying security structure architecture is unstable. While there is a technical solution, all work to date is flawed. This will impact several future business service offerings. What should the product owner do to resolve this?
Options
- AAsk the development team to address the issue since it is in their domain.
- BReview the project's risk matrix, and follow the steps outlined in the risk mitigation plan.
- CMeet with the team and stakeholders to address rework and rewrite stories as needed.
- DCancel the current sprint, and meet with stakeholders to reassess the project's validity.
How the community answered
(33 responses)- A3% (1)
- B9% (3)
- C82% (27)
- D6% (2)
Explanation
A foundational architectural defect that invalidates all prior work and threatens future business services is a high-stakes issue that requires collective decision-making. The product owner must bring together the team and stakeholders to transparently assess the scope of rework, reprioritize the backlog, and rewrite affected stories. This collaborative approach maintains trust and ensures all impacted parties contribute to the solution. Option A (delegate to dev team alone) excludes stakeholders who are directly affected. Option B (follow the existing risk plan) is likely insufficient for a newly discovered, systemic architectural failure. Option D (cancel sprint) is premature - the severity must first be understood collaboratively before such drastic action is taken.