During an iteration, an agile team discovers infrastructure requirements that were not initially considered. What should the team do to effectively manage this?
The correct answer is B. Add these requirements into the product backlog for future consideration. Agile change management must go though the backlog refinement for prioritization.
Submitted by parkjh· Apr 18, 2026Adaptive Planning
Question
During an iteration, an agile team discovers infrastructure requirements that were not initially considered. What should the team do to effectively manage this?
Options
- ARework the iteration scope to accommodate these requirements.
- BAdd these requirements into the product backlog for future consideration.
- CRaise the discovery of these requirements as an issue, and escalate to management.
- DImmediately start working on these requirements.
How the community answered
(50 responses)- B94% (47)
- C2% (1)
- D4% (2)
Explanation
Agile change management must go though the backlog refinement for prioritization.
Topics
#Product Backlog Management#Adaptive Planning#Requirements Discovery#Iteration Management