PMI-ACP · Question #712

What should the agile practitioner know about tracking velocity?

The correct answer is C. A team that consistently meets its planned velocity is more efficient than a team that consistently. Velocity is an internal planning tool that is not comparable across teams - different teams size stories differently, so a team with velocity 50 is not inherently more or less efficient than a team with velocity 25 (eliminating A and B). A team that consistently meets its…

Submitted by viktor_hu· Apr 18, 2026Team Performance

Question

What should the agile practitioner know about tracking velocity?

Options

  • AA team with an average velocity of 50 is twice as efficient as a team with an average velocity of
  • BA team with an average velocity of 50 is equally as efficient as a team with an average velocity of
  • CA team that consistently meets its planned velocity is more efficient than a team that consistently
  • DA team that consistently meets its planned velocity is less efficient than a team that constantly

How the community answered

(53 responses)
  • A
    6% (3)
  • B
    4% (2)
  • C
    89% (47)
  • D
    2% (1)

Explanation

Velocity is an internal planning tool that is not comparable across teams - different teams size stories differently, so a team with velocity 50 is not inherently more or less efficient than a team with velocity 25 (eliminating A and B). A team that consistently meets its planned velocity demonstrates predictability, reliable estimation, and stable throughput - which are hallmarks of efficiency and maturity. A team that consistently misses its velocity has a planning or execution problem. Option D inverts this logic incorrectly.

Topics

#Velocity tracking#Agile metrics#Team predictability#Consistent delivery

Community Discussion

No community discussion yet for this question.