An agile team is working well together, but productivity has been flat. What can the project leader do to help them improve performance?

The correct answer is B. Chair a weekly team retrospective focusing on identifying areas for continuous improvement. Retrospectives are the core agile mechanism for continuous improvement. When productivity is flat despite good team dynamics, it signals a need for structured reflection on process, not just relationship health. A weekly retrospective focused on identifying improvement areas…

Submitted by kavita_s· Apr 18, 2026Continuous Improvement

Question

An agile team is working well together, but productivity has been flat. What can the project leader do to help them improve performance?

Options

  • AReview the burndown chart to identify ways to increase efficiency.
  • BChair a weekly team retrospective focusing on identifying areas for continuous improvement.
  • CAsk a senior manager to initiate a root-cause analysis.
  • DIdentify team key performance indicators (KPIs) and create positive incentives when targets are

How the community answered

(34 responses)
  • A
    3% (1)
  • B
    79% (27)
  • C
    12% (4)
  • D
    6% (2)

Explanation

Retrospectives are the core agile mechanism for continuous improvement. When productivity is flat despite good team dynamics, it signals a need for structured reflection on process, not just relationship health. A weekly retrospective focused on identifying improvement areas gives the team a regular, time-boxed forum to surface inefficiencies, experiment with process changes, and track results. Reviewing the burndown chart (A) diagnoses symptoms but does not produce improvement actions. Escalating to a senior manager for root-cause analysis (C) undermines team autonomy and is disproportionate. Creating KPI-based incentives (D) can undermine intrinsic motivation and team cohesion, which contradicts agile values.

Topics

#Retrospectives#Continuous Improvement#Team Performance#Agile Facilitation