PMI-ACP · Question #708
An agile team is working well together, but productivity has been flat. What can the project leader do to help them improve performance?
The correct answer is B. Chair a weekly team retrospective focusing on identifying areas for continuous improvement. Retrospectives are the core agile mechanism for continuous improvement. When productivity is flat despite good team dynamics, it signals a need for structured reflection on process, not just relationship health. A weekly retrospective focused on identifying improvement areas…
Question
An agile team is working well together, but productivity has been flat. What can the project leader do to help them improve performance?
Options
- AReview the burndown chart to identify ways to increase efficiency.
- BChair a weekly team retrospective focusing on identifying areas for continuous improvement.
- CAsk a senior manager to initiate a root-cause analysis.
- DIdentify team key performance indicators (KPIs) and create positive incentives when targets are
How the community answered
(34 responses)- A3% (1)
- B79% (27)
- C12% (4)
- D6% (2)
Explanation
Retrospectives are the core agile mechanism for continuous improvement. When productivity is flat despite good team dynamics, it signals a need for structured reflection on process, not just relationship health. A weekly retrospective focused on identifying improvement areas gives the team a regular, time-boxed forum to surface inefficiencies, experiment with process changes, and track results. Reviewing the burndown chart (A) diagnoses symptoms but does not produce improvement actions. Escalating to a senior manager for root-cause analysis (C) undermines team autonomy and is disproportionate. Creating KPI-based incentives (D) can undermine intrinsic motivation and team cohesion, which contradicts agile values.