nerdexam
PMIPMI

PMI-ACP · Question #707

PMI-ACP Question #707: Real Exam Question with Answer & Explanation

The correct answer is D: Ask the product owner for approval to proceed.. The product owner is the authority on scope, value, and trade-offs. When the team identifies changes that add value but affect schedule, that is a prioritization decision — which is squarely in the product owner's domain. The agile project leader's role is to facilitate this co

Submitted by alyssa_d· Apr 18, 2026Value-driven Delivery

Question

During an iteration planning meeting, the team suggests changes to add product value that will require extra work and impact the schedule. What should the agile project leader do?

Options

  • ARe-estimate the project.
  • BFinish the product as it was initially planned.
  • CTry to include as many changes as possible.
  • DAsk the product owner for approval to proceed.

Explanation

The product owner is the authority on scope, value, and trade-offs. When the team identifies changes that add value but affect schedule, that is a prioritization decision — which is squarely in the product owner's domain. The agile project leader's role is to facilitate this conversation, not make unilateral scope or schedule decisions. Re-estimating the entire project (A) is premature and disproportionate for mid-iteration suggestions. Ignoring the changes (B) misses a value opportunity. Including as many changes as possible (C) disregards schedule impact and the product owner's authority over the backlog.

Topics

#Product Owner responsibility#Change management#Value prioritization#Iteration planning

Community Discussion

No community discussion yet for this question.

Full PMI-ACP PracticeBrowse All PMI-ACP Questions