PMI-ACP · Question #705
The agile practitioner has determined that two different team members are working on addressing the same major issue on the project. How should the agile practitioner address this?
The correct answer is D. Document all project issues in a common space and ask the team members to decide on task. The agile approach favors transparency and team self-organization. Documenting the issue in a shared, visible space (such as an issue log or Kanban board) and letting the team collaboratively decide on ownership leverages the team's collective intelligence and avoids the…
Question
The agile practitioner has determined that two different team members are working on addressing the same major issue on the project. How should the agile practitioner address this?
Options
- AImplement a burnup chart and add the issue resolution as a task to the product backlog for the
- BAdd the issue to the kanban board and assign it to the team member who has made the most
- CConduct a root-cause analysis on the issue and identify related risks and risk response owners at
- DDocument all project issues in a common space and ask the team members to decide on task
How the community answered
(48 responses)- A13% (6)
- B6% (3)
- C2% (1)
- D79% (38)
Explanation
The agile approach favors transparency and team self-organization. Documenting the issue in a shared, visible space (such as an issue log or Kanban board) and letting the team collaboratively decide on ownership leverages the team's collective intelligence and avoids the facilitator becoming a single point of control. This promotes accountability and shared understanding. Adding it to the product backlog (A) mixes operational issues with feature work. Assigning it based on effort invested (B) is an arbitrary metric that bypasses team input. Root-cause analysis (C) is valuable but does not directly solve the immediate duplicate-effort problem.
Topics