PMI-ACP Question #7: Real Exam Question with Answer & Explanation
The correct answer is C: Add the risk in a clearly visible location and ensure it is discussed after the next daily stand. In Agile, risks are typically managed with transparency and minimal ceremony. When a business analyst identifies a new risk, the best first step is to make it visible — such as posting it on the team's risk board or information radiator — and ensure it gets discussed at the n
Question
A business analyst has identified a new risk in an Agile project. What is the best first step the business analyst should take regarding this risk?
Options
- ACall a meeting with the project manager and senior management to determine how the risk
- BEmail the project manager and add it to the risk register so that it is discussed during the
- CAdd the risk in a clearly visible location and ensure it is discussed after the next daily stand
- DCall an immediate meeting with all team members to discuss the newly identified risk.
Explanation
In Agile, risks are typically managed with transparency and minimal ceremony. When a business analyst identifies a new risk, the best first step is to make it visible — such as posting it on the team's risk board or information radiator — and ensure it gets discussed at the next appropriate Agile ceremony (e.g., after the daily standup or in the next sprint review). Calling an immediate all-hands meeting (D) is disruptive and unnecessary for most risks. Escalating directly to senior management (A) skips the team. Emailing only the PM (B) reduces visibility. Answer C balances transparency with Agile ceremony cadence.