PMI-ACP · Question #8

What are the primary outputs of a release planning session?

The correct answer is D. Risks, action items, dependencies, and Release Backlog. A release planning session in Agile produces the artifacts needed to coordinate delivery across multiple iterations. The primary outputs are: risks identified during planning, action items that need follow-up, dependencies between stories or teams, and the Release Backlog (the se

Submitted by tarun92· Apr 18, 2026Adaptive Planning

Question

What are the primary outputs of a release planning session?

Options

  • ARelease vision, assumptions, action items, and iteration goals
  • BPrioritized Product Backlog, risks, action items, and release goals
  • CEstimated iteration velocities, risks, action items, and Release Backlog
  • DRisks, action items, dependencies, and Release Backlog

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    8% (2)
  • D
    88% (22)

Explanation

A release planning session in Agile produces the artifacts needed to coordinate delivery across multiple iterations. The primary outputs are: risks identified during planning, action items that need follow-up, dependencies between stories or teams, and the Release Backlog (the set of stories targeted for the release). While a Prioritized Product Backlog and iteration velocity estimates may be inputs or discussed, they are not the primary outputs of release planning. Answer D most accurately captures the tangible deliverables from a release planning session.

Topics

#Release Planning#Agile Artifacts#Backlog Management#Risk Management