PMI-ACP · Question #524
This management approach is based on knowing well defined goals but not the means for a solution.
The correct answer is D. Agile Project Management. Agile Project Management (D) applies when the goal or objective is clearly defined, but the solution path-the 'how'-is uncertain and must be discovered iteratively. This is the distinguishing factor in Wysocki's framework: APM covers Iterative and Adaptive PMLC models where…
Question
This management approach is based on knowing well defined goals but not the means for a solution.
Options
- ATraditional Project Management
- BEmertxe Project Management
- CExtreme Project Management
- DAgile Project Management
How the community answered
(55 responses)- A4% (2)
- B2% (1)
- C5% (3)
- D89% (49)
Explanation
Agile Project Management (D) applies when the goal or objective is clearly defined, but the solution path-the 'how'-is uncertain and must be discovered iteratively. This is the distinguishing factor in Wysocki's framework: APM covers Iterative and Adaptive PMLC models where goals are known. Traditional Project Management (A) has both goals and solutions well-defined. Extreme Project Management (C, xPM) is used when neither goal nor solution is clear. Emertxe/MPx (B) represents an even higher degree of ambiguity beyond xPM.