Pick the two PMLC models that are based upon the Agile Project Management (APM) approach:

The correct answer is B. Adaptive. In Wysocki's PMLC framework, the five models are: Linear, Incremental (both Traditional/TPM), Iterative, Adaptive (both APM-based), and Extreme (xPM). The two APM-based models are Iterative (D) and Adaptive (B)-both are used when the goal is reasonably clear but the solution is…

Submitted by kwame.gh· Apr 18, 2026Agile Principles and Mindset

Question

Pick the two PMLC models that are based upon the Agile Project Management (APM) approach:

Options

  • ALinear
  • BAdaptive
  • CIncremental
  • DIterative

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    90% (19)
  • D
    5% (1)

Explanation

In Wysocki's PMLC framework, the five models are: Linear, Incremental (both Traditional/TPM), Iterative, Adaptive (both APM-based), and Extreme (xPM). The two APM-based models are Iterative (D) and Adaptive (B)-both are used when the goal is reasonably clear but the solution is not fully defined upfront. The Linear (A) model corresponds to classic waterfall/TPM. The Incremental (C) model is also TPM-based, delivering in phases but with a fully defined scope. Note: the exam key lists only B, but standard Wysocki classification includes both B and D as the APM models.

Topics

#PMLC Models#Agile Life Cycles#Adaptive Life Cycles#Agile Project Management