PMI-ACP · Question #488

There must be a release every Sprint.

The correct answer is B. False. Scrum requires that a 'Done' and potentially releasable increment is produced every Sprint, but an actual release to production is not mandatory. The decision of whether to release an increment is a business decision made by the Product Owner based on factors like market…

Submitted by packet_pusher· Apr 18, 2026Agile Principles and Mindset

Question

There must be a release every Sprint.

Options

  • ATrue
  • BFalse

How the community answered

(60 responses)
  • A
    12% (7)
  • B
    88% (53)

Explanation

Scrum requires that a 'Done' and potentially releasable increment is produced every Sprint, but an actual release to production is not mandatory. The decision of whether to release an increment is a business decision made by the Product Owner based on factors like market timing, stakeholder needs, or accumulated value. The increment must be in a releasable state, but releasing it is optional.

Topics

#Sprint#Release Management#Agile Delivery#Scrum