PMI-ACP · Question #488
There must be a release every Sprint.
The correct answer is B. False. Scrum requires that a 'Done' and potentially releasable increment is produced every Sprint, but an actual release to production is not mandatory. The decision of whether to release an increment is a business decision made by the Product Owner based on factors like market…
Question
There must be a release every Sprint.
Options
- ATrue
- BFalse
How the community answered
(60 responses)- A12% (7)
- B88% (53)
Explanation
Scrum requires that a 'Done' and potentially releasable increment is produced every Sprint, but an actual release to production is not mandatory. The decision of whether to release an increment is a business decision made by the Product Owner based on factors like market timing, stakeholder needs, or accumulated value. The increment must be in a releasable state, but releasing it is optional.