No one, not even the Scrum Master, tells the development team how to build the product.
The correct answer is A. True. The Development Team is self-organizing. Scrum empowers the team to determine how they will accomplish their work - no one outside the team dictates implementation details, technical practices, or task assignments. The Scrum Master serves the team by removing impediments and…
Question
No one, not even the Scrum Master, tells the development team how to build the product.
Options
- ATrue
- BFalse
How the community answered
(49 responses)- A86% (42)
- B14% (7)
Explanation
The Development Team is self-organizing. Scrum empowers the team to determine how they will accomplish their work - no one outside the team dictates implementation details, technical practices, or task assignments. The Scrum Master serves the team by removing impediments and coaching Scrum practices, but does not direct the technical work. The Product Owner defines 'what' is built; the Development Team decides 'how' it is built.
Topics
Community Discussion
No community discussion yet for this question.