The correct answer is A: Transparency, Inspection, and Adaption. The three official pillars of Scrum, as defined in the Scrum Guide, are Transparency, Inspection, and Adaptation - not 'Adaption.' While this appears to be a spelling distinction, the official terminology matters in certification exams. Option B lists Empiricism, which IS a found
Question
Which of the following is NOT part of the Scrum Framework?
Options
- ATransparency, Inspection, and Adaption
- BTransparency, Inspection, and Empiricism
- CTransparency, Acceptance and Adaptation
- DRetrospectives, Inspection, and Adaptation
Explanation
The three official pillars of Scrum, as defined in the Scrum Guide, are Transparency, Inspection, and Adaptation - not 'Adaption.' While this appears to be a spelling distinction, the official terminology matters in certification exams. Option B lists Empiricism, which IS a foundational principle of Scrum (Scrum is grounded in empirical process theory). Option C introduces 'Acceptance,' which is not a Scrum pillar. Option D mixes Retrospectives (a Scrum event) with pillars. The key takeaway: only 'Transparency, Inspection, and Adaptation' (correctly spelled) represent the three pillars.
Topics
Community Discussion
No community discussion yet for this question.