PMI-ACP · Question #403
Which artifact is useful for seeing total project risk increasing or decreasing over time?
The correct answer is C. Risk Burndown Graph. A Risk Burndown Graph plots total risk exposure over time across the entire project. As risks are mitigated, retired, or realized, the graph shows whether aggregate risk is trending down (the desired outcome) or unexpectedly rising. A Burndown bar chart tracks remaining work…
Question
Which artifact is useful for seeing total project risk increasing or decreasing over time?
Options
- ABurndown bar chart
- BRisk Burn-Up chart
- CRisk Burndown Graph
- DRisk Map
How the community answered
(63 responses)- A5% (3)
- B2% (1)
- C92% (58)
- D2% (1)
Explanation
A Risk Burndown Graph plots total risk exposure over time across the entire project. As risks are mitigated, retired, or realized, the graph shows whether aggregate risk is trending down (the desired outcome) or unexpectedly rising. A Burndown bar chart tracks remaining work (not risk). A Risk Burn-Up chart is not a standard artifact. A Risk Map (such as a probability/impact matrix) is a snapshot tool for visualizing individual risks at a point in time, not a trend view of total project risk over the project lifecycle.