On a risk map or a risk heat map, the vertical and horizontal axes represent:

The correct answer is B. Probability and Impact. A risk heat map is a standard risk visualization tool where one axis represents the Probability (or Likelihood) of a risk occurring, and the other axis represents the Impact (or Severity/Consequence) if it does occur. Risks are plotted in the resulting grid, producing a…

Submitted by klara.se· Apr 18, 2026Adaptive Planning

Question

On a risk map or a risk heat map, the vertical and horizontal axes represent:

Options

  • AEffort and Impact
  • BProbability and Impact
  • CProbability and Exposure
  • DImpact and Exposure

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    89% (31)
  • C
    3% (1)
  • D
    6% (2)

Explanation

A risk heat map is a standard risk visualization tool where one axis represents the Probability (or Likelihood) of a risk occurring, and the other axis represents the Impact (or Severity/Consequence) if it does occur. Risks are plotted in the resulting grid, producing a color-coded 'heat' pattern - high probability + high impact risks appear in the 'hot' (red) zone. This two-dimensional view helps teams prioritize which risks need the most attention. Options like Exposure and Effort are not the defining axes of this standard tool.

Topics

#Risk Management#Risk Map#Probability#Impact