PMI-ACP · Question #37
PMI-ACP Question #37: Real Exam Question with Answer & Explanation
The correct answer is D: Release. In Agile EVM, progress is measured at the Release level because EVM metrics (Planned Value, Earned Value, Actual Cost) are most meaningful when tracking cumulative progress toward a releasable product increment over a longer time horizon. Measuring at the Task level (A) is too gr
Question
When using Agile Earned Value Management (EVM), progress should be measured at which level?
Options
- ATask
- BIteration
- CProduct
- DRelease
Explanation
In Agile EVM, progress is measured at the Release level because EVM metrics (Planned Value, Earned Value, Actual Cost) are most meaningful when tracking cumulative progress toward a releasable product increment over a longer time horizon. Measuring at the Task level (A) is too granular and unstable. Measuring at the Iteration level (B) is useful for velocity but not for formal EVM. Measuring at the Product level (C) is too broad. The Release provides the right granularity to plan the budget baseline, track earned value, and forecast completion.
Topics
Community Discussion
No community discussion yet for this question.