The correct answer is A: A pull system. A pull system is a method of organizing work where team members pull the next available task from a queue (such as a Kanban board) when they have capacity, rather than having work pushed or assigned to them by a manager. This promotes self-organization, reduces bottlenecks, and e
Question
Setting up development work in a way that the team can figure out what to do next is called:
Options
- AA pull system
- BPush system
- CCritical path
- DSprint backlog
Explanation
A pull system is a method of organizing work where team members pull the next available task from a queue (such as a Kanban board) when they have capacity, rather than having work pushed or assigned to them by a manager. This promotes self-organization, reduces bottlenecks, and ensures work flows naturally based on the team's actual capacity. It is contrasted with a push system, where work is scheduled and assigned top-down regardless of current capacity.
Topics
Community Discussion
No community discussion yet for this question.