PMI-ACP Question #319: Real Exam Question with Answer & Explanation

The correct answer is A: A pull system. A pull system is a method of organizing work where team members pull the next available task from a queue (such as a Kanban board) when they have capacity, rather than having work pushed or assigned to them by a manager. This promotes self-organization, reduces bottlenecks, and e

Submitted by khalil_dz· Apr 18, 2026Agile Principles and Mindset

Question

Setting up development work in a way that the team can figure out what to do next is called:

Options

  • AA pull system
  • BPush system
  • CCritical path
  • DSprint backlog

Explanation

A pull system is a method of organizing work where team members pull the next available task from a queue (such as a Kanban board) when they have capacity, rather than having work pushed or assigned to them by a manager. This promotes self-organization, reduces bottlenecks, and ensures work flows naturally based on the team's actual capacity. It is contrasted with a push system, where work is scheduled and assigned top-down regardless of current capacity.