Agile best practices such as iterative planning and review activities is called:

The correct answer is B. Organic risk management. Organic Risk Management refers to risk management that is built naturally into the Agile process itself through its iterative practices - such as short sprints, frequent reviews, continuous integration, and regular retrospectives. Because these activities surface problems early…

Submitted by mike_84· Apr 18, 2026Agile Principles and Mindset

Question

Agile best practices such as iterative planning and review activities is called:

Options

  • AInherent risk management
  • BOrganic risk management
  • COvert risk management
  • DIntrinsic risk management

How the community answered

(32 responses)
  • A
    6% (2)
  • B
    91% (29)
  • D
    3% (1)

Explanation

Organic Risk Management refers to risk management that is built naturally into the Agile process itself through its iterative practices - such as short sprints, frequent reviews, continuous integration, and regular retrospectives. Because these activities surface problems early and frequently, risk is managed organically rather than through a separate, formal risk management process. This contrasts with Overt Risk Management (C), which involves explicit, planned risk processes. 'Inherent' and 'Intrinsic' are not standard Agile risk management categories.

Topics

#Agile Risk Management#Iterative Development#Agile Principles#Adaptive Planning

Community Discussion