PMI-ACP · Question #259
PMI-ACP Question #259: Real Exam Question with Answer & Explanation
The correct answer is B: Following a plan. This is a direct reference to the Agile Manifesto's four core value statements. The fourth value explicitly states: 'Responding to change over following a plan.' The other options appear in different Manifesto values: 'Customer collaboration over contract negotiation' (A vs. C) a
Question
In Agile project management, responding to change is valued over __________.
Options
- AContract negotiation
- BFollowing a plan
- CCustomer collaboration
- DProcesses and tools
Explanation
This is a direct reference to the Agile Manifesto's four core value statements. The fourth value explicitly states: 'Responding to change over following a plan.' The other options appear in different Manifesto values: 'Customer collaboration over contract negotiation' (A vs. C) and 'Individuals and interactions over processes and tools' (D). The Manifesto does not reject plans — it simply values adaptability more highly.
Topics