The correct answer is B: Following a plan. This is a direct reference to the Agile Manifesto's four core value statements. The fourth value explicitly states: 'Responding to change over following a plan.' The other options appear in different Manifesto values: 'Customer collaboration over contract negotiation' (A vs. C) a

Submitted by emma.c· Apr 18, 2026Agile Principles and Mindset

Question

In Agile project management, responding to change is valued over __________.

Options

  • AContract negotiation
  • BFollowing a plan
  • CCustomer collaboration
  • DProcesses and tools

Explanation

This is a direct reference to the Agile Manifesto's four core value statements. The fourth value explicitly states: 'Responding to change over following a plan.' The other options appear in different Manifesto values: 'Customer collaboration over contract negotiation' (A vs. C) and 'Individuals and interactions over processes and tools' (D). The Manifesto does not reject plans — it simply values adaptability more highly.

Topics

#Agile Manifesto#Agile Values#Responding to change#Adaptive planning