nerdexam
PMIPMI

PMI-ACP · Question #235

PMI-ACP Question #235: Real Exam Question with Answer & Explanation

The correct answer is B: Time-box events. The seven Lean principles include: Eliminate Waste, Amplify Learning, Decide as Late as Possible (Delay Commitment), Deliver as Fast as Possible, Empower the Team, Build Integrity In, and See the Whole. 'Time-boxing events' (B) is a Scrum concept, not a Lean principle.

Submitted by joshua94· Apr 18, 2026Agile Principles and Mindset

Question

Which is NOT a principle of Lean?

Options

  • AEliminate waste
  • BTime-box events
  • CDeliver fast
  • DDelay commitment

Explanation

The seven Lean principles include: Eliminate Waste, Amplify Learning, Decide as Late as Possible (Delay Commitment), Deliver as Fast as Possible, Empower the Team, Build Integrity In, and See the Whole. 'Time-boxing events' (B) is a Scrum concept, not a Lean principle.

Topics

#Lean principles#Waste elimination#Delay commitment#Agile practices

Community Discussion

No community discussion yet for this question.

Full PMI-ACP PracticeBrowse All PMI-ACP Questions