PMI-ACP · Question #216
PMI-ACP Question #216: Real Exam Question with Answer & Explanation
The correct answer is D: Illustrate the project risk profile and new and changing risks.. A risk burndown chart in Agile is a visualization tool that plots the overall risk exposure of a project over time, showing the aggregate risk profile as iterations progress. It captures both the reduction of known risks and the emergence of new or changing risks — making optio
Question
In Agile risk management, a risk burndown chart is best used to:
Options
- AQualitatively analyze the probability of a risk occurring.
- BTrack progress on risk reduction of technical risks.
- CDocument the external risks that could impact the project.
- DIllustrate the project risk profile and new and changing risks.
Explanation
A risk burndown chart in Agile is a visualization tool that plots the overall risk exposure of a project over time, showing the aggregate risk profile as iterations progress. It captures both the reduction of known risks and the emergence of new or changing risks — making option D the most accurate description. It is not primarily used for qualitative probability analysis (A), which is done through risk registers or probability/impact matrices. Tracking technical risk reduction specifically (B) is too narrow. Documenting external risks (C) is a risk register function, not a burndown chart.
Topics
Community Discussion
No community discussion yet for this question.