In a vision meeting, the vision for the project is defined and presented by the:
The correct answer is C. customer. In Agile, the project vision originates from and is owned by the customer (or Product Owner representing the customer). The vision meeting is where the customer articulates the business goal, the problem to be solved, and the desired outcomes. This is a customer-driven activity,
Question
In a vision meeting, the vision for the project is defined and presented by the:
Options
- Amanagement
- Bproject manager
- Ccustomer
- Dproject team
How the community answered
(58 responses)- A2% (1)
- B5% (3)
- C91% (53)
- D2% (1)
Explanation
In Agile, the project vision originates from and is owned by the customer (or Product Owner representing the customer). The vision meeting is where the customer articulates the business goal, the problem to be solved, and the desired outcomes. This is a customer-driven activity, not a management or project manager function. Management (A) may sponsor or support the project, the project manager (B) facilitates delivery, and the project team (D) builds toward the vision - but the vision itself belongs to the customer. This reinforces the Agile principle of customer collaboration and business-driven prioritization.