PMI-ACP · Question #2
The team estimation game method mainly consists of a:
The correct answer is A. Pile of cards with user, capability, and value to be prioritized by the project team. The Team Estimation Game is a relative estimation technique that uses a deck of cards, each representing a user story, feature, or backlog item with associated information (such as user, capability, and value). Team members collaboratively sort and prioritize these cards by…
Question
The team estimation game method mainly consists of a:
Options
- APile of cards with user, capability, and value to be prioritized by the project team.
- BSpreadsheet with backlog issues to be prioritized and each to be given a prioritizationnumber.
- CWhite board session where iterations are estimated and related to the project road map.
- DBrainstorm session where resources are related to prioritized work packages.
How the community answered
(31 responses)- A90% (28)
- C3% (1)
- D6% (2)
Explanation
The Team Estimation Game is a relative estimation technique that uses a deck of cards, each representing a user story, feature, or backlog item with associated information (such as user, capability, and value). Team members collaboratively sort and prioritize these cards by placing them in order of size or complexity. This physical, visual method encourages team discussion and consensus without anchoring bias. It is distinct from Planning Poker (which uses numeric point cards) and from whiteboard or spreadsheet-based methods.