PMI-ACP · Question #1

PMI-ACP Question #1: Real Exam Question with Answer & Explanation

The correct answer is D: Avoid them and have resources assigned to only one project at a time.. In Agile, fractional assignments (splitting a person's time across multiple projects) are considered harmful because they introduce context-switching overhead, reduce focus, impair team cohesion, and slow overall throughput. Agile principles emphasize dedicated, cross-functional

Submitted by asante_acc· Apr 18, 2026Team Performance

Question

What is the ideal approach for an Agile project manager to take when considering fractional assignments?

Options

  • ADo nothing, as fractional assignments will not impact project performance.
  • BAllow resources to be assigned to no more than two projects at a time.
  • COnly allow nonessential resources to be fractionally assigned.
  • DAvoid them and have resources assigned to only one project at a time.

Explanation

In Agile, fractional assignments (splitting a person's time across multiple projects) are considered harmful because they introduce context-switching overhead, reduce focus, impair team cohesion, and slow overall throughput. Agile principles emphasize dedicated, cross-functional teams working on one project at a time to maximize flow and minimize waste. While options B and C might seem like reasonable compromises, the ideal Agile approach (answer D) is to avoid fractional assignments entirely and keep resources fully committed to a single project.

Topics

#Fractional assignments#Dedicated teams#Context switching#Team focus