How is the Retrospective meeting BEST conducted?

The correct answer is A. Set the stage, Gather data, Generate Insights, Decide on what to do, Close the Retrospective. The standard Retrospective format, as defined by Esther Derby and Diana Larsen in 'Agile Retrospectives,' follows five sequential phases: (1) Set the stage - create a safe environment; (2) Gather data - collect facts and feelings; (3) Generate Insights - identify root causes…

Submitted by tarun92· Apr 18, 2026Continuous Improvement

Question

How is the Retrospective meeting BEST conducted?

Options

  • ASet the stage, Gather data, Generate Insights, Decide on what to do, Close the Retrospective
  • BGather data, Generate Insights, Decide on what to do, Set the stage, Close the Retrospective
  • CSet the stage, Gather data, Decide on what to do, Generate Insights, Close the Retrospective
  • DDecide on what to do, Set the stage, Gather data, Generate Insights, Close the Retrospective

How the community answered

(48 responses)
  • A
    88% (42)
  • B
    4% (2)
  • C
    2% (1)
  • D
    6% (3)

Explanation

The standard Retrospective format, as defined by Esther Derby and Diana Larsen in 'Agile Retrospectives,' follows five sequential phases: (1) Set the stage - create a safe environment; (2) Gather data - collect facts and feelings; (3) Generate Insights - identify root causes; (4) Decide on what to do - agree on actionable improvements; (5) Close the Retrospective - summarize and appreciate. This order ensures insights are grounded in data before decisions are made.

Topics