Feature X has a value of 12 and the total value of all features is 35. If the feature is estimated to cost 56%, what is the priority of this feature using relative weighting?

The correct answer is B. 0.61. Relative weighting priority is calculated as: Priority = Value% / Cost%. First, compute the feature's value percentage: 12 / 35 ≈ 0.3429 (34.29%). The cost percentage is given as 56% (0.56). Priority = 0.3429 / 0.56 ≈ 0.61. A higher ratio means better value for money, making…

Submitted by takeshi77· Apr 18, 2026Value-driven Delivery

Question

Feature X has a value of 12 and the total value of all features is 35. If the feature is estimated to cost 56%, what is the priority of this feature using relative weighting?

Options

  • A0.34
  • B0.61
  • C1.64
  • D0.625

How the community answered

(16 responses)
  • B
    88% (14)
  • C
    6% (1)
  • D
    6% (1)

Explanation

Relative weighting priority is calculated as: Priority = Value% / Cost%. First, compute the feature's value percentage: 12 / 35 ≈ 0.3429 (34.29%). The cost percentage is given as 56% (0.56). Priority = 0.3429 / 0.56 ≈ 0.61. A higher ratio means better value for money, making this feature moderately prioritized.