PMI-ACP · Question #191
Feature X has a value of 12 and the total value of all features is 35. If the feature is estimated to cost 56%, what is the priority of this feature using relative weighting?
The correct answer is B. 0.61. Relative weighting priority is calculated as: Priority = Value% / Cost%. First, compute the feature's value percentage: 12 / 35 ≈ 0.3429 (34.29%). The cost percentage is given as 56% (0.56). Priority = 0.3429 / 0.56 ≈ 0.61. A higher ratio means better value for money, making…
Question
Feature X has a value of 12 and the total value of all features is 35. If the feature is estimated to cost 56%, what is the priority of this feature using relative weighting?
Options
- A0.34
- B0.61
- C1.64
- D0.625
How the community answered
(16 responses)- B88% (14)
- C6% (1)
- D6% (1)
Explanation
Relative weighting priority is calculated as: Priority = Value% / Cost%. First, compute the feature's value percentage: 12 / 35 ≈ 0.3429 (34.29%). The cost percentage is given as 56% (0.56). Priority = 0.3429 / 0.56 ≈ 0.61. A higher ratio means better value for money, making this feature moderately prioritized.
Topics