PMI-ACP · Question #146
PMI-ACP Question #146: Real Exam Question with Answer & Explanation
The correct answer is B: team. Agile emphasizes self-organizing, empowered teams. Project values — such as quality, collaboration, and transparency — are most effectively implemented when the team collectively defines and commits to them. Values imposed by a sponsor (A), project manager (C), or a prescribe
Question
In an Agile approach, project values are most effectively implemented when they are determined by the:
Options
- Asponsor
- Bteam
- Cproject manager
- Dmethodology
Explanation
Agile emphasizes self-organizing, empowered teams. Project values — such as quality, collaboration, and transparency — are most effectively implemented when the team collectively defines and commits to them. Values imposed by a sponsor (A), project manager (C), or a prescribed methodology (D) lack the team's buy-in and ownership, making them harder to sustain. When the team determines their own values, those values become intrinsic to how they work rather than external mandates.
Topics
Community Discussion
No community discussion yet for this question.