PMI-ACP · Question #123

PMI-ACP Question #123: Real Exam Question with Answer & Explanation

The correct answer is C: Product Owner. The Product Owner (PO) is solely responsible for managing and prioritizing the Product Backlog, which includes deciding which user stories are included in each iteration. The PO represents business and stakeholder interests, ensuring the team works on the highest-value items firs

Submitted by yuriko_h· Apr 18, 2026Value-driven Delivery

Question

Who is responsible for prioritizing the stories that will be included in the iteration?

Options

  • AScrumMaster
  • BDeveloper
  • CProduct Owner
  • DTeam

Explanation

The Product Owner (PO) is solely responsible for managing and prioritizing the Product Backlog, which includes deciding which user stories are included in each iteration. The PO represents business and stakeholder interests, ensuring the team works on the highest-value items first. The ScrumMaster facilitates the process, the Developer estimates and executes, and the Team collectively decides how much work to take on — but prioritization authority belongs exclusively to the Product Owner.

Topics

#Product Owner#Story Prioritization#Iteration Planning#Scrum Roles