PMI-ACP · Question #123
PMI-ACP Question #123: Real Exam Question with Answer & Explanation
The correct answer is C: Product Owner. The Product Owner (PO) is solely responsible for managing and prioritizing the Product Backlog, which includes deciding which user stories are included in each iteration. The PO represents business and stakeholder interests, ensuring the team works on the highest-value items firs
Question
Who is responsible for prioritizing the stories that will be included in the iteration?
Options
- AScrumMaster
- BDeveloper
- CProduct Owner
- DTeam
Explanation
The Product Owner (PO) is solely responsible for managing and prioritizing the Product Backlog, which includes deciding which user stories are included in each iteration. The PO represents business and stakeholder interests, ensuring the team works on the highest-value items first. The ScrumMaster facilitates the process, the Developer estimates and executes, and the Team collectively decides how much work to take on — but prioritization authority belongs exclusively to the Product Owner.
Topics
Community Discussion
No community discussion yet for this question.