PMI-ACP · Question #122
PMI-ACP Question #122: Real Exam Question with Answer & Explanation
The correct answer is A: Release planning, Iteration planning, and Estimation. Release planning (roadmap-level scheduling of stories into releases), iteration planning (selecting and committing to stories for the upcoming sprint), and estimation (sizing stories via story points or relative sizing) are all core Agile planning practices. The other options mix
Question
Which of the following is a list of valid Agile project planning practices?
Options
- ARelease planning, Iteration planning, and Estimation
- BEstimation, Spike Solutions, and Iteration planning
- CIteration planning, Continuous Integration, and Estimation
- DVision, Release planning, and Performance Optimization
Explanation
Release planning (roadmap-level scheduling of stories into releases), iteration planning (selecting and committing to stories for the upcoming sprint), and estimation (sizing stories via story points or relative sizing) are all core Agile planning practices. The other options mix in non-planning activities: spike solutions are a development/research technique, continuous integration is an engineering practice, and performance optimization is a technical activity — none of these are project planning practices.