The correct answer is B: The principles of each are often complementary.. Scrum and XP are separate but highly complementary frameworks that are frequently used together. Scrum provides the project management and process framework (sprints, ceremonies, roles), while XP contributes engineering practices (TDD, pair programming, continuous integration, re

Submitted by tyler.j· Apr 18, 2026Agile Principles and Mindset

Question

What is the best description of the relationship between Scrum and extremeProgramming(XP)?

Options

  • AXP is a component of Scrum.
  • BThe principles of each are often complementary.
  • CScrum is a component of XP.
  • DThe principles of each are often contradictory.

Explanation

Scrum and XP are separate but highly complementary frameworks that are frequently used together. Scrum provides the project management and process framework (sprints, ceremonies, roles), while XP contributes engineering practices (TDD, pair programming, continuous integration, refactoring). Neither is a component of the other — they operate at different levels and reinforce each other rather than conflicting.

Topics

#Scrum#Extreme Programming (XP)#Agile Methodologies#Methodology Comparison

Community Discussion

No community discussion yet for this question.

Full PMI-ACP PracticeBrowse All PMI-ACP Questions