nerdexam
MicrosoftMicrosoft

PL-500 · Question #59

PL-500 Question #59: Real Exam Question with Answer & Explanation

The correct answer is A: Yes. Parallel branches allow two independent Update Row actions to execute simultaneously, directly minimizing total processing time.

Develop automations

Question

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution. After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen. You are creating a cloud flow that will use two Update Row actions to interact with Microsoft Dataverse. Neither of these actions are dependent on each other. You must minimize the amount of processing time require to complete the flow. You need to implement the actions in the cloud flow. Solution: Create a parallel branch for the two Update Row actions. Does the solution meet the goal?

Options

  • AYes
  • BNo

Explanation

Parallel branches allow two independent Update Row actions to execute simultaneously, directly minimizing total processing time.

Common mistakes.

  • B. Selecting No is incorrect because parallel branches are precisely the Power Automate construct designed to run independent actions simultaneously, making this the optimal solution for reducing total flow execution time.

Concept tested. Parallel branch execution in Power Automate cloud flows

Reference. https://learn.microsoft.com/en-us/power-automate/parallel-modern-approvals

Topics

#Power Automate Cloud flows#Parallel branches#Performance optimization#Dataverse actions

Community Discussion

No community discussion yet for this question.

Full PL-500 PracticeBrowse All PL-500 Questions