Which of the following is captured when baselining a project?

The correct answer is A. KPI. When a project is baselined, Key Performance Indicators (KPIs) are defined and captured to establish measurable criteria for evaluating project success and performance. KPIs serve as the benchmarks against which all future performance is measured. The other options are not…

Project Management Concepts

Question

Which of the following is captured when baselining a project?

Options

  • AKPI
  • BSV
  • CBAC
  • DAC

How the community answered

(29 responses)
  • A
    90% (26)
  • C
    7% (2)
  • D
    3% (1)

Explanation

When a project is baselined, Key Performance Indicators (KPIs) are defined and captured to establish measurable criteria for evaluating project success and performance. KPIs serve as the benchmarks against which all future performance is measured. The other options are not captured at baseline: SV (Schedule Variance) is a calculated metric used during execution monitoring, not established at baseline; BAC (Budget at Completion) is an input to the cost baseline rather than something 'captured by' the baseline process; and AC (Actual Cost) is tracked during project execution, not at baseline.

Topics

#Project Baselining#Key Performance Indicators (KPIs)#Project Planning#Performance Measurement