PK0-005 · Question #84

A developer identifies new code that will enhance performance, will not be visible to the user group, and can be done without impact to the timeline. Which of the following steps should the project…

The correct answer is A. Log a change request. Any change to the project's scope - even a beneficial, invisible, or seemingly low-risk one - must go through formal change control. The PM must log a change request first so the change can be reviewed, approved, and properly tracked. Authorizing the change without formal…

Project Management Concepts

Question

A developer identifies new code that will enhance performance, will not be visible to the user group, and can be done without impact to the timeline. Which of the following steps should the project manager take FIRST?

Options

  • ALog a change request.
  • BOpen a project issue.
  • CAuthorize the new code.
  • DAdd the change to the schedule.

How the community answered

(22 responses)
  • A
    77% (17)
  • B
    5% (1)
  • C
    5% (1)
  • D
    14% (3)

Explanation

Any change to the project's scope - even a beneficial, invisible, or seemingly low-risk one - must go through formal change control. The PM must log a change request first so the change can be reviewed, approved, and properly tracked. Authorizing the change without formal approval bypasses governance. Even if the developer believes it won't impact the timeline, that assessment must be validated through the change control process. Only after approval should the change be scheduled or implemented.

Topics

#Change management#Project change control#Project manager responsibilities#Project governance