PK0-005 · Question #634
PK0-005 Question #634: Real Exam Question with Answer & Explanation
The correct answer is A: Start the project closure.. Once all project deliverables are completed, the next action is to formally begin the project closure process, which includes acceptance, documentation, and administrative closeout
Project Life Cycle Phases
Question
Which of the following is the next action a project manager should take once all deliverables for a project are completed?
Options
- AStart the project closure.
- BPerform the quality audit review.
- CAsk the customer for additional information.
- DDeliver training to the operations team.
Explanation
Once all project deliverables are completed, the next action is to formally begin the project closure process, which includes acceptance, documentation, and administrative closeout
Topics
#Project closure#Project life cycle phases#Project management processes